Thursday, April 28, 2016

Panauti Hydro Electricity Project

Introduction

Name : Panauti Bijuli Ghar
Built in: 2022 B.S.
Made by: Russia
Location: Khopasi, Balthali (20 minutes Bus ride from Panauti Bus Park to Khopasi Bus Stop and 5 minutes walking down the road)
Installed Capacity: 2400 KW( 3 units(turbine) 800 KW each )
Daily Pondage Capacity: 50000 Cu. Meters
Canal Discharge : 3.2 Cubic meters/sec
Length of canal (Basen To Barrage): 3721 meters
Effective head:6o meters
Maximum head: 66 meters
Length of Penstock: 370 meters
Internal Diameter of Penstock: 1400 mm
Turbine Capacity: 850 KW
Type of wheel(turbine): Francis
Discharge of each unit: 1.61 cu.m/sec
Generation Voltage : 6300 Volts
Transmisssion voltage: 33000 volts up to Bkt Sub, 11000 volts upto Sangha
Step Up transformers: 6300/33000 Volts (2*1500 KVA), 6300/11000 Volts (2*650 KVA)





Reservoir
Reservoir is around 300 m upside of the power house station. The reservoir is dry( less water) most of the months so electricity is not produced 24 hours a day(few hours a day). Approx. calculation estimates its capacity to be 10M liter.




For entering the project area/power house station you need to write a letter to the office and then they will give you the entry order.




Problems described by Local

Photo Gallery of our Visit
We visited the Panauti on the date 2073:01:15 to find some ideas regarding the project. Some of the photes clicked are:










No comments:

Post a Comment